Since the beginning of the year in the construction of the Ust-Srednekanskaya HPS was put 54,000 cubic meters of concrete |
|
|
|
Thursday, 09 December 2010 |
To run the first unit in 2012, must still 130,000 cubic meters. Due to stable funding for hydrobuilders have every chance to carry out planned - reports Vitaliy Kholoimov, “Magadanskaya pravda”.
As told Alexander Fedorov, the chief engineer of public corporation "Ust-SrednekanGESstroy”, the construction goes on all objects, including the spillway, station, dead of the dam, outlet channel, station platform, approaching drainage tunnel.
РИА "Север ДВ"
|